Tutzpatz, 79.31MWP, Germany

Client:

Tutzpatz Power Plant

Location:

17091 Tützpatz, Germany

Duration:

14 Months

Challenge:

Large‑scale international project spanning over a year with varying seasonal conditions. Soft soil and rainfall required careful logistics and coordination with multinational contractors.

Tasks:

Structure assembly, module mounting, and DC cabling installation.

Site Area:

555 Acres

DC Power Capacity:

79.31 MWp

Total Panels Installed:

126,896 Panels

Average Manpower:

150 People