Tutzpatz, 79.31MWP, Germany
Client:
Tutzpatz Power Plant
Location:
17091 Tützpatz, Germany
Duration:
14 Months
Challenge:
Large‑scale international project spanning over a year with varying seasonal conditions. Soft soil and rainfall required careful logistics and coordination with multinational contractors.
Tasks:
Structure assembly, module mounting, and DC cabling installation.
Site Area:
555 Acres
DC Power Capacity:
79.31 MWp
Total Panels Installed:
126,896 Panels
Average Manpower:
150 People