Schönermark, 80MWP, Germany
Client:
Schönermark Power Plant
Location:
Schönermark, Germany
Duration:
6 Months
Challenge:
Short‑duration, large‑scale project with winter start and spring rains creating muddy conditions. Coordination with international contractors to complete within 6 months.
Tasks:
Structure assembly, module mounting, and DC cabling installation.
Site Area:
560 Acres
DC Power Capacity:
80 MWP
Total Panels Installed:
128,000 Panels
Average Manpower:
150 People