Resko Solar Plant, 51.7MWP, Sosnowo and Sosnówko, RESKO, Poland

Client:

Resko Solar Plant

Location:

Sosnowo and Sosnówko, RESKO, Poland

Duration:

11 Months

Challenge:

Large‑scale solar project across Sosnowo and Sosnówko in Poland, facing wet winter conditions and logistical challenges. Coordination with international contractors over a 2‑year construction period.

Tasks:

Structure assembly, module mounting, and DC cabling installation.

Site Area:

105 Acres

DC Power Capacity:

51.7 MWP

Total Panels Installed:

82,720 Panels

Average Manpower:

100 People

At HST Nordic (559519-9372), we engineer, procure, and construct high-impact renewable energy and industrial projects across Sweden and beyond. As part of a globally recognized industrial group, we deliver turnkey solar, BESS, and green infrastructure solutions that power progress.