Larendeel,38MWP, Netherland
Client:
Larendeel Power Plant
Location:
Larendeel, Netherland
Duration:
3 Months
Challenge:
Ongoing project with summer start and expected autumn/winter challenges, including soft soil and rainfall. Coordination with international contractors under a tight construction schedule.
Tasks:
Structure assembly, module mounting, and DC cabling installation.
Site Area:
94 Acres
DC Power Capacity:
38 MWP
Total Panels Installed:
21,472 Panels
Average Manpower:
55 People