Kirikmaë, 77MWP Lääneranna, Estonia

Client:

Kirikmaë Power Plant

Location:

Lääneranna, Estonia

Duration:

13 Months

Challenge:

Large‑scale solar development in Estonia with seasonal weather challenges, including heavy autumn rains and winter frost. Coordination with multiple international contractors over a 1‑year+ schedule.

Tasks:

Structure assembly, module mounting, and DC cabling installation.

Site Area:

546 Acres

DC Power Capacity:

77.9 MWP

Total Panels Installed:

124,640 Panels

Average Manpower:

140 People

At HST Nordic (559519-9372), we engineer, procure, and construct high-impact renewable energy and industrial projects across Sweden and beyond. As part of a globally recognized industrial group, we deliver turnkey solar, BESS, and green infrastructure solutions that power progress.