Fluitenberg, 33.49MWP, Netherland

Client:

Fluitenberg Power Plant

Location:

Fluitenberg, Netherlands

Duration:

7 Months

Challenge:

Soft ground and muddy conditions during spring and autumn rains. Coordination with multiple international teams to meet a 6‑month construction schedule.

Tasks:

Structure assembly, module mounting, and DC cabling installation.

Site Area:

225 Acres

DC Power Capacity:

33.49 MWP

Total Panels Installed:

51,472 Panels

Average Manpower:

90 People