Exloermond, 20MWP, Netherlands
Client:
Exloermond Power Plant
Location:
Exloermond, Netherlands
Duration:
5 Months
Challenge:
Soft soil and muddy conditions after spring rains. Coordinating multiple international teams under a short 5‑month construction schedule.
Tasks:
Structure assembly, module mounting, and DC cabling installation.
Site Area:
140 Acres
DC Power Capacity:
20 MWP
Total Panels Installed:
32,000 Panels
Average Manpower:
70 People