Challenge:

Cold winter conditions with muddy terrain at the start of construction. Coordination with multiple international teams under a tight 5‑month schedule.

Tasks:

Structure assembly, module mounting, and DC cabling installation.

Site Area:

105 Acres

DC Power Capacity:

14.9 MWP

Total Panels Installed:

23,840 Panels

Average Manpower:

60 People