Dievelman, 14.9MWP, Netherland
Client:
Dievelman Power Plant
Location:
Dievelman, Netherland
Duration:
5 Months
Challenge:
Cold winter conditions with muddy terrain at the start of construction. Coordination with multiple international teams under a tight 5‑month schedule.
Tasks:
Structure assembly, module mounting, and DC cabling installation.
Site Area:
105 Acres
DC Power Capacity:
14.9 MWP
Total Panels Installed:
23,840 Panels
Average Manpower:
60 People