Buinerhorn, 6.6 MWP,Netherlands
Client:
Buinerhorn Power Plant
Location:
Buinerhorn, Netherlands
Duration:
5 Months
Challenge:
Muddy terrain and frequent spring rainfall. Coordinating international teams under a tight 5‑month construction schedule.
Tasks:
Structure assembly, module mounting, and DC cabling installation.
Site Area:
46 Acres
DC Power Capacity:
6.6 MWP
Total Panels Installed:
10,560 Panels
Average Manpower:
40 People