Bajdy2,6.05MWP, Poland

Client:

Bajdy2

Location:

Zalewo Commune, Iława County, Warmian-Masurian Voivodeship, Poland

Duration:

6 Months

Challenge:

Medium‑scale solar project in Poland with summer start and expected winter challenges, including heavy rain, mud, and short daylight hours. Coordination with international contractors under a 9‑month schedule.

Tasks:

Structure assembly, module mounting, and DC cabling installation.

Site Area:

42 Acres

DC Power Capacity:

6.05 MWP

Total Panels Installed:

9,680 Panels

Average Manpower:

35 People