Alphen, 8MWP, Netherland

Client:

Alphen Power Plant

Location:

Alphen, Netherland

Duration:

3 Months

Challenge:

Short construction timeline with intermittent spring rainfall. Coordination with international contractors under a compact 3‑month schedule.

Tasks:

Structure assembly, module mounting, and DC cabling installation.

Site Area:

56 Acres

DC Power Capacity:

8 MWP

Total Panels Installed:

12,800 Panels

Average Manpower:

40 People