Alphen, 8MWP, Netherland
Client:
Alphen Power Plant
Location:
Alphen, Netherland
Duration:
3 Months
Challenge:
Short construction timeline with intermittent spring rainfall. Coordination with international contractors under a compact 3‑month schedule.
Tasks:
Structure assembly, module mounting, and DC cabling installation.
Site Area:
56 Acres
DC Power Capacity:
8 MWP
Total Panels Installed:
12,800 Panels
Average Manpower:
40 People